• Agile Meets Waterfall: Governance for Hybrid Delivery Programmes
    Programme Governance Hybrid Delivery

    The real question isn't Scrum versus the V-Model — it's how both worlds work together inside one programme, instead of teams working against each other.

    In regulated technical environments (for example under quality models such as ASPICE), development teams increasingly work in an agile way, while approvals, supplier contracts and milestones still need to be steered through a phase-based model. In these programmes, I build a shared governance layer that synchronises both delivery models instead of pitting them against each other.

    • A shared milestone calendar that both sprints and phase gates feed into.
    • Requirements and change traceability that shows the same status in both worlds (for example via a linked DOORS/Jira set-up).
    • Clear interface roles between the Product Owner (agile) and the programme/change board (phase-based).
    • Early-warning indicators rather than status colours: trend before state.
    • Escalation paths that bind both sides equally.
    CHALLENGE

    Teams that each deliver excellent technical work but past each other, because sprint outcomes and approval milestones don't feed the same calendar.

    APPROACH

    A lean, shared governance layer: one schedule backbone, one source of truth for requirements and status, clearly assigned decision rights.

    BENEFIT

    Reliable commitments to customers and management, without either team having to give up its preferred way of working.

    Do your teams work in sprints while releases run on phase gates? Where exactly that breaks is usually quick to name — an intro call, or the project health check first.

    ASPICE · V-Model · Scrum/Kanban · Hybrid Delivery · Requirements Engineering · Change Management · Programme Governance
  • Stabilising Critical Programmes in 90 Days: A Practical Roadmap
    Turnaround Interim Management

    The first 90 days decide whether a programme becomes governable again — or whether trust and deadlines keep eroding.

    As an interim manager, I typically take over programmes where transparency, delivery reliability or stakeholder trust has broken down. A structured 90-day roadmap restores control quickly, without overloading the team further.

    • Days 1–15 – Diagnosis: a stocktake of scope, resources, open risks and the actual status (not the reported one).
    • Days 16–45 – Governance build-up: establish a schedule, clear accountabilities (RACI), a reporting cadence and escalation paths from scratch.
    • Days 46–75 – Stabilisation: deliver visible quick wins, actively manage the critical path, synchronise suppliers and interfaces.
    • Days 76–90 – Proof: deliver credible milestones and rebuild trust with the customer/management through facts, not announcements.
    • Throughout: a single source of truth for status – no conflicting reports to different stakeholders.
    CHALLENGE

    Programmes without a credible schedule, fragmented accountabilities and a history of broken commitments.

    APPROACH

    Build governance from zero, make the critical path and dependencies visible, and put decisions where the information actually is.

    BENEFIT

    From flying blind to a governable, traceable set-up – measurable within a quarter.

    At the start of a roadmap like this? The project health check gives you a first read in two minutes, and an intro call covers the rest.

    Turnaround Management · Crisis Stabilisation · Governance Build-up · Milestone Recovery · Interim Management · Task Force Leadership
  • Leading International Matrix Organisations: Governance Across Time Zones, Cultures and Supply Chains
    International Programmes Leadership

    Leading a programme across several time zones, cultures and supplier tiers is first a governance question — collaboration comes second.

    In international programmes with teams spread across Europe, Asia and the US, a good schedule alone is not enough. What matters is a structure that brings together different working hours, communication styles and escalation cultures without slowing any single team down.

    • A binding, cross-time-zone rhythm for status, decisions and escalations (rather than purely ad-hoc communication).
    • Clear interface roles between the internal team, Tier-2/Tier-3 suppliers and the customer organisation.
    • Actively accounting for cultural differences in feedback and escalation behaviour, rather than ignoring them.
    • Supplier negotiation as an integral part of programme management, not a separate silo.
    • One shared language for status and risk, regardless of who is reporting from where.
    CHALLENGE

    Distributed teams across Germany, India, China and the US, including Tier-2 partners, with no shared rhythm for decisions and escalations.

    APPROACH

    A cross-time-zone governance structure with clear interfaces, unambiguous decision rights and a single point of contact for key stakeholders.

    BENEFIT

    Reliable delivery despite a complex, international supply chain – and a team that feels led, not just managed.

    If your programme is drifting apart across sites and time zones, an intro call is enough for me to place where governance has to take hold first.

    International Programmes · Matrix Organisation · Cross-Cultural Team Leadership · Supplier Management · Escalation Management · Cross-Border Leadership
  • What ASPICE Level 2 actually demands day to day – and where it usually fails
    ASPICE V-model Traceability

    You do not pass an assessment with documents. You pass it with a development organisation that genuinely works the way the documents claim.

    The V-model is often misread as the opposite of agile. What it actually describes first of all is a symmetry: every specification level on the descending branch has a corresponding verification level on the ascending one. Customer requirement and system test, system architecture and integration test, software detailed design and unit test. Whoever elaborates the left-hand side has thereby committed to the right.

    That coupling is exactly where things break in practice – and almost never for lack of will. It breaks for lack of connection between tools and responsibilities. Requirements live in one system, architecture in a second, test cases in a third, and changes travel by email. Each level on its own is maintained perfectly well. It is just that nobody can answer which test covers which requirement in under two days.

    An assessor does not ask whether a document exists. He asks whether one work product follows consistently from the previous one, and whether the organisation can show that without a week of preparation. That, at heart, is the difference between Level 1 and Level 2: Level 1 means the work gets done. Level 2 means it is managed – planned, monitored, with defined work products under configuration control.

    • Bidirectional traceability that holds in both directions: from customer requirement through to test case and back again – not as a spreadsheet reconstructed afterwards, but as a by-product of the daily work.
    • A change process that moves requirement, architecture, test and schedule together. A change that only reaches the requirements tool is not a change; it is an inconsistency with a delay built in.
    • Work products under configuration control, with a defined maturity. „Version 0.9, for the past eight months“ is a process finding, not an interim state.
    • Roles that are actually staffed. A process that assumes a configuration manager who does not exist describes a different organisation from the one in the room.
    • Metrics somebody reads. Figures collected only for the assessment are the first thing an assessment notices.
    CHALLENGE

    Organisations that can produce every required work product but cannot show how one follows from another. The process description is clean; the development that actually happens runs alongside it.

    APPROACH

    Move traceability to where the work already happens instead of bolting it on at the end of the project. Link the tools rather than maintain spreadsheets, make the change process the only route by which scope can move, and train project leads and engineers so they understand the purpose rather than just filling in the field.

    BENEFIT

    An assessment becomes a stocktake rather than a project. More valuable day to day: the question ‚what breaks if we change this requirement?‘ becomes answerable in minutes – and that is the real reason the discipline pays for itself.

    Assessment coming up, or one that went badly? An intro call is enough for an honest read on how far the road actually is.

    ASPICE Level 2 · Automotive SPICE · V-model · Bidirectional traceability · Requirements engineering · Configuration management · Change management · ISO 26262 · Assessment preparation
  • Getting software into a vehicle: release governance for OTA under UN R155/156
    OTA / FOTA UN R155/156 Release governance

    A bug in an app costs you an update. A bug in a vehicle rollout costs you a recall – and during an update a car is not a phone. It belongs to somebody, and it has to work tomorrow morning.

    Over-the-air updates are often treated as a solved problem: the technology works, the rest is logistics. In reality OTA shifts the load from development into release. As long as software was flashed at the end of the production line, start of production was the boundary. With OTA every delivery changes a fleet that is already with customers – across several countries, with different type-approval states, different hardware states, and a way back that is expensive or absent.

    UN R155 and R156 turn this into a regulatory obligation: a cyber security management system and a software update management system, both demonstrable, both auditable. Which in practice means the question ‚who decided, when, and on what basis, that this build goes to two million vehicles?‘ has to be answerable at any moment – answerable, not reconstructable.

    The governance for that is unspectacular, and effective precisely because of it. At its core it is a handful of agreements kept consistently, rather than an extensive process framework that gets bypassed when it matters.

    • Pre-integration cycles that find defects before a release date depends on them. Integration is a rhythm, not a phase at the end.
    • Change-freeze windows ahead of critical delivery gates – binding, with a defined and documented exception route instead of a culture of quiet exceptions.
    • Vulnerability and patch management on production systems, running separately from the feature release. A security patch must not wait for the next feature drop.
    • Regional requirements early rather than late: operating, certification and data requirements differ substantially by market, and they belong in the schedule rather than trailing it.
    • A fallback that has been rehearsed. A rollback nobody has ever exercised is an assumption, not a plan.
    • Evidence as a by-product: who decided, on what data, accepting what residual risk – captured at the moment of the decision, not weeks later for the audit.
    CHALLENGE

    Several customer programmes on shared infrastructure, separate production environments per region, validation cycles running for months – and alongside them development teams able to deliver faster than the release chain can pass them through.

    APPROACH

    Set the rhythm rather than mediate it: fixed integration cycles, binding freeze windows ahead of gates, separate routes for security and feature deliveries, and reporting that shows the trend rather than the status. Escalation becomes a planned step, not a relationship problem.

    BENEFIT

    Delivery reliability that holds even across validation cycles measured in months, a security state that does not wait for the next feature state, and an evidence base that survives an audit without a team spending weeks assembling it first.

    If your update process is heading into release or currently stuck: book an intro call — no obligation.

    OTA · FOTA · Software update management system · SUMS · CSMS · UN R155 · UN R156 · Cloud-to-vehicle · AWS · Release management · Change freeze · Patch management · Rollout control
  • The coffee corner is not small talk: how to reach the real information in the first weeks
    Starting a mandate Team access Remote leadership

    A status report tells you what somebody was willing to write down. What people actually believe, you learn somewhere else – and usually in passing.

    When an external arrives in a programme that is in trouble, the team has no particular reason to tell him the uncomfortable truth. Quite the opposite: an interim manager is often read as the bearer of bad news, sometimes as the advance party for consequences. In that position you get exactly the information that is already in the report – and it is rarely the information you need.

    The sentences that matter are not spoken in the status meeting. They are spoken at the coffee machine, in the corridor, in the five minutes before a meeting starts: ‚we have actually known since March that the date will not hold.‘ ‚That interface has never worked, we just never measured it.‘ Sentences like that are not gossip; they are the working basis. Without them you plan against a position nobody in the room believes.

    So informal access to the team is not a pleasant side effect for me, it is part of the method. It does not come from friendliness alone. It comes from dealing with uncomfortable facts factually and visibly, early on, instead of carrying them upwards. Once somebody has seen that an honest answer brings no trouble, they speak up sooner the next time – and that gain in time is the whole point.

    There is a second thing that decides whether you get access at all. An external is eyed at first as the new consultant who turns up with slides and unrealistic ideas. Engineers, though, open up to someone who understands what they are talking about. My route through electrician, state-certified technician and several years as a development and test engineer helps here more than any methodology training: I can push and follow up without the demand missing technical reality – and I can tell the difference between ‚that is not possible‘ and ‚we would rather not‘. Both occur, and each needs a different answer.

    On distributed programmes this channel does not appear by itself, but it can be built. In Teams it works if you set it up deliberately: be there five minutes before the meeting starts, leave the call open after the formal part, hold short one-to-ones with no agenda. It is no substitute for the corridor, but it comes close enough – and across time zones it is often the only option there is.

    • Listen more than you direct in the first days. Change the process immediately and you will not hear anything after that.
    • One-to-ones with no agenda and no minutes – deliberately short, deliberately unstructured.
    • Be early on the call and stay after the formal part. For distributed teams, the start and the end of a meeting are the coffee corner.
    • A channel that is not the status channel. Where status gets reported, thinking does not happen.
    • What arrives informally does not become a basis for decisions until it has been verified – and it is never used against the person who said it. That is precisely what decides whether the channel stays open.
    • Keep confidence, upwards too. The value of this access lies in it not becoming a reporting line.
    CHALLENGE

    A programme whose official position and actual position have drifted apart – and a team with no reason to explain that to an external in week one.

    APPROACH

    Build personal access before you need it: listen, keep commitments, make uncomfortable answers consequence-free. With distributed teams, deliberately create the same space instead of missing it.

    BENEFIT

    Reliable information weeks earlier than the reporting line delivers it – and a team that raises problems while they are still solvable rather than once they have escalated.

    Starting a difficult mandate yourself, or looking for someone to take one on? Let us talk it through — book a call.

    Interim management · Starting a mandate · Onboarding · Team access · Informal communication · Remote leadership · Microsoft Teams · Distributed teams · Crisis projects · Building trust
  • Task force blueprint: stabilising hardware/software interfaces in trouble
    Task Force Industrial Automation

    Interface chaos between hardware, firmware and cloud is not an automotive phenomenon. The pattern repeats in industrial automation, smart energy and anywhere devices sit in the field — and the blueprint against it is the same.

    When a programme tips over at the hardware/software boundary, it is rarely for want of technical skill. It is because nobody has defined, bindingly, which software state belongs to which hardware state, who may release a change, and how a field failure finds its way back into engineering. A task force closes that gap — not through more reporting, but through less room for interpretation.

    • Week one: a binding version and configuration matrix — which software state is released for which hardware state, and who decided that.
    • One single source of defects instead of three parallel lists held by engineering, manufacturing and service.
    • A daily 15-minute cross-discipline sync with fixed participants that replaces status reports rather than adding to them.
    • Field returns recorded with a cause assignment rather than a symptom description — otherwise engineering optimises in the wrong place.
    • A defined end: the criteria under which the task force is dissolved and responsibility handed back to the line organisation.
    CHALLENGE

    Inconsistent version states across hardware, firmware and backend, a rising field return rate, and three organisational units each able to argue plausibly that the problem sits elsewhere.

    APPROACH

    A time-boxed task force with a clear mandate, cross-discipline staffing and decision rights — plus a shared configuration and defect baseline that all parties commit to.

    BENEFIT

    Statements about what is actually running in the field that hold up, a falling return rate, and an organisation able to maintain that state once the task force is gone.

    Want a first read yourself? The project health check takes two minutes. For the supplier side there is the assessment grid as an Excel template. And if you recognise these symptoms, an intro call is enough for me to place your situation — no obligation.

    Task force · Hardware/software integration · Industrial automation · Smart energy · IoT · Configuration management · Field returns · Escalation management · Multi-vendor governance
  • Playbook: making a software programme with thousands of open defects governable again
    Defect Management Turnaround

    A backlog with a five-figure ticket count is not a quality problem, it is a prioritisation problem. The question is not how to work through all of it — but what you consciously decide not to work through.

    On an infotainment programme at Harman/Daimler I brought a backlog of more than 10,000 tickets down by 85 % without moving the start of production. The lever was not additional developer capacity but a different sorting logic: not by reporting date or by the seniority of the reporter, but by what the end customer actually experiences.

    • ABC classification by customer-perceivable impact — not by the internal severity rating, which usually comes from whoever raised the ticket.
    • Rigorous merging of duplicates: one real defect, one ticket, however many times it was reported.
    • A daily integration routine, so fixes do not sit in branches for weeks and create new defects when merged.
    • Plan explicitly around offshore bottlenecks: use the time difference as a rhythm rather than accepting it as an excuse.
    • A documented decision not to fix something is a result — it simply has to be taken deliberately and defended towards the customer.
    CHALLENGE

    A backlog growing faster than it is worked off, and a management team that can no longer read production readiness from the ticket count.

    APPROACH

    Re-sorting by customer-perceivable impact, duplicate cleanup, daily integration, and explicit decisions about what deliberately stays open.

    BENEFIT

    A ticket count that means something again, a start of production that holds, and a release decision based on facts rather than hope.

    If your backlog is heading in this direction, an intro call is enough for a first assessment.

    Defect management · Defect backlog · Prioritisation · Turnaround · Embedded software · Start of production · SOP · Integration management · Offshore steering
  • Interim manager or conventional project manager? A decision aid
    Interim Management Role Clarity

    Both roles lead a programme. The difference lies in whether the conditions for leading are still in place at all — and who restores them.

    A conventional project manager drives a programme along a plan the organisation believes in. That very foundation is missing in crisis programmes: the plan exists, but nobody considers it realistic. An interim manager first restores governability — a status you can rely on, clear decision rights, an escalation path that works — and leads after that.

    • Interim makes sense when the reporting is no longer believed and dates slip without an identifiable cause.
    • Interim makes sense when decisions stall between departments because nobody is formally accountable.
    • Interim makes sense when the role has to voice uncomfortable facts without weighing internal career interests.
    • Conventional project management is enough when plan and reality broadly match and only capacity is missing.
    • Typical mistake: trying to solve it internally for too long — the later the decision, the more expensive the stabilisation.
    CHALLENGE

    The decision is usually made under pressure and treated as a staffing question, when it is in fact a question about the state of governance.

    APPROACH

    Match the role to the state: if capacity is missing, project management helps. If governability is missing, it takes someone external with a mandate and no internal ties.

    BENEFIT

    A deliberate role decision rather than a makeshift one — and a defined end, because interim mandates are designed around handover.

    Unsure which role your situation calls for? That is usually quick to place in a short call.

    Interim management · Role clarity · Crisis projects · Programme leadership · Governance · Decision rights · Escalation · Handover